Howard Energy Logo
HOWARD ENERGY CORP.     
 
 
 





 

Deep Well Project in the Illinois Basin
Galum Creek Project - Perry County Illinois


WELL DATA

Howard Energy Corporation
P.O. Box 693
Mt. Carmel, Illinois 62863-0693

Shaglee Unit #1
Section 5-T5S-R4W
Perry County, Illinois

MORNING REPORT SUMMARY


Historical Data

November, 2001

DAY:
DATE:
                                       OPERATION:
29.
11/23
6062' TD, Drilled into Granite, Bottom 700' of formations were gone, will make a decision by 9:00 a.m. Currently logging, does not look favorable
28.
11/22

Depth 6020' Drilling 6-7 minutes per foot, drilling shales, silt stones and dolomite, should TD sometime late Friday or early Saturday.

Happy Thanksgiving!

27.
11/21
Depth 5888' Drilling 6-7 minutes per foot, presently tripping for bit
26.
11/20

Depth 5676' Drilling 4-5 minutes per foot

Potasi Dolomite - slight show of gas, drilling ahead 5-7 minutes per foot

25.
11/19
Depth 5435' Drilling 5-7 minutes per foot, tripped for bit last 24 hours
24.
11/18
Depth 5309' Drilling 8-9 minutes per foot, slight show of gas in the Oneida, presently drillling into the top of the Cambrian.
23.
11/17
Depth 5062' Drilling 4-5 minutes per foot, no show
22.
11/16
8:00 a.m. Depth 4940' - no shows Drilling 5 minutes per ft.
21.
11/15
Depth 4630' Drilling 4-5 minutes per foot
10:00 a.m. Depth 4660' - slight show of oil in Knox not good enough to test
20.
11/14

We expect the St. Peter @ 4100+ late this morning

Depth 4475 drilling 4-5 minutes per foot Drilled throught St. Peter, no show, into top of Knox at 4300' presently at 4500', getting ready to trip for bit

19.
11/13

Depth 3820' Drilling 3 minutes per foot 4100' should be St. Peter later today

Depth 4020' Drilling 3-4 minutes per foot Trip for bit

18.
11/12
Depth 3796' Drilling 3 minutes per foot Barlow 1089' +12 St. Gen 1389' +22 Borden 2044' + 80' Trenton 3410 + 100' Show of gas in the Trenton Black River 3518' + 100'
17.
11/11
Depth 3333' Drilling 2 minutes per foot
16.
11/10
Depth 2920' Drilling 3-4 minutes per foot
15.
11/9
Depth 2597' Drilling 3-4 minutes per foot, Trip for bit
14.
11/8
Depth 2334' Drilling 3-4 minutes per foot
13.
11/7
Depth 1943' Drilling 2-3 minutes per foot, Trip for Bit
12.
11/6
Depth 1616', trip for bit, drilling 3-4 minutes per foot
11.
11/5
Depth 1304' Set 1304' of 8 5/8" casing ready to start drilling
10.
11/4
Depth 1304' Ready to run 8 5/8" casing
9.
11/3
Depth 1188' Drilling 5-7 minutes per foot
8.
11/2
1068' drilling 6-8 minutes per foot
7.
11/1
1161' @ 4 minutes per foot Hole deviated 6.25 degrees Shut down, plug back with cement to 1000' at 8:00 a.m. Waiting on cement to set to start drilling again.
6.
10/31
Drilling at 973' at 4 minutes per foot.
5.
10/30
Surface pipe came loose. Had to reset surface pipe. Back to drilling @ 700' at 5:45 a.m.
4.
10/29
Depth 505'; Drilling 1 minute per foot 12 1/4" hole.
3.
10/28
Depth 48'; start drilling 17 1/2" hole @ 7:00 p.m. Set 48' of 13 3/8" casing, cement with 60 sacks 3" calcium Ca Cl2 with plug down & 12:15 a.m. presenlty nipple up & will start drilling 12 1/4" hole.
2.
10/27
Finish rigging up, set steel pits and start drilling 17 1/2" hole.
1.
10/26
Will finish moving rig to location and rig up.
.
10/25
Continue moving equipment, did not start rigging up due to heavy rain and storms. Will rig up tomorrow.
.
10/24
Continue moving rig 14 to location and start rig up.
.
10/23
Start moving Rig 14 to location and begin building location.

 

    



Howard Energy Corp.